Hyperscale Data Converts Michigan Mining Site to AI Compute Under SEC-Disclosed Contract

Hyperscale Data halts Bitcoin mining at Dowagiac to deploy 20 MW AI capacity; June filing details contract terms, costs, and conditional long-term revenue potential.

Hyperscale Data Halts Michigan Bitcoin Mining to Convert Site for AI Compute

Hyperscale Data is stopping Bitcoin mining at its Dowagiac, Michigan campus to redirect the energized site toward a contracted AI and high-performance computing deployment.

The company sold 65 BTC for about $5.1 million. A June 24 SEC filing disclosed a subsidiary agreement to deploy 20 MW of AI compute in two 10 MW phases, with an option for an additional 32 MW. The initial term is 10 years plus two 5-year extensions.

Contract Terms and Capital Context

The filing states potential revenue could exceed $1.2 billion only if the agreement runs its maximum term. It also lists a $5 million upfront service charge and a $5.6 million security deposit. Estimated cost for the initial 20 MW deployment is $100-120 million, with roughly 60,000 square feet to be retrofitted.

The company is expected to continue mining at its Montana facility. The Michigan move therefore reflects site-specific portfolio management rather than a broader exit from Bitcoin mining.

Open Questions

Exact construction timeline, delivery milestones, and customer identity remain undisclosed. It is also unknown whether the Michigan pivot signals a wider strategy across other mining sites or remains limited to this location.